Road Projects

Dáil Éireann Debate, Tuesday - 5 July 2022

Tuesday, 5 July 2022

Ceisteanna (158)

Alan Kelly

Ceist:

158. Deputy Alan Kelly asked the Minister for Transport when the Shannon crossing construction will commence. [36277/22]

Amharc ar fhreagra

Freagraí scríofa

As announced by the Minister for Public Expenditure and Reform on the 23rd May, the Office for Government Procurement has published guidance for parties to public works contracts on establishing and using an 'Inflation/Supply Chain Delay Co-operation Framework Agreement'.  Clare County Council, which is the contracting authority for the Shannon Crossing, Killaloe Bypass and R494 Upgrade scheme, are in discussions with the contractor on the basis of the guidance material and consideration of the co-operation agreement as well as how the project will be programmed and progressed. 