277. Deputy Darren O'Rourke asked the Minister for Transport to provide a breakdown by year of the stages of the proposed MetroLink project, including the planning, procurement and construction phases; and if he will make a statement on the matter. [37621/22]

Amharc ar fhreagra

Freagraí scríofa

A detailed delivery timeline for MetroLink has not yet been finalised as the project has only just received Decision Gate 1 Approval under the Public Spending Code. The timeline below shows the expected key dates of the process, but some of these will be dependent on the planning process.

- September 2022 – Submission of Railway Order application

- 2023 – Decision by Government at Decision Gate 2 of the Public Spending Code

- 2025 – Award of contracts

A detailed design, planning, and procurement strategy will be prepared for Decision Gate 2 in line with the Public Spending Code. Following Decision Gate 3 and an enforceable Railway Order, the winning tenders will be awarded to enable construction to begin by the end of 2025.

The above dates are dependent upon the timing and outcome of the planning process, and whether or not any judicial or other legal proceeding are commenced in relation to that planning process.

As Minister for Transport, I have responsibility for policy and overall funding in relation to public transport. The National Transport Authority (NTA) has statutory responsibility for the planning and development of public transport infrastructure in the Greater Dublin Area which includes, in conjunction with Transport Infrastructure Ireland, MetroLink.

Noting the NTA's responsibility in the matter, I have referred the Deputy's question to the NTA for a more detailed direct reply to the specific issues raised. Please contact my private office if you do not receive a reply within 10 days.

A referred reply was forwarded to the Deputy under Standing Order 51