Schools Building Projects

Dáil Éireann Debate, Tuesday - 27 September 2022

Tuesday, 27 September 2022

Ceisteanna (282)

Pádraig Mac Lochlainn

Ceist:

282. Deputy Pádraig Mac Lochlainn asked the Minister for Education if she will provide an update on the plans for new school buildings at a school (details supplied), including a timeframe for the commencement of construction and completion of works. [47335/22]

Amharc ar fhreagra

Freagraí scríofa

The school referred to by the Deputy is currently at Stage 3 (tender action and award).

Following changes to the Planning Acts, introduced in September 2021, a new application for planning permission is required, which is being finalised by the Design Team.

A new tender process, including the shortlisting of contractors, will run parallel with the new planning application. The new prequalification notices have been published on e-tenders.

Subject to no issues arising, it is envisaged that works could commence on site in Quarter 2 of 2023 with a completion timeframe of approximately 27 months.