391. Deputy Joe Flaherty asked the Minister for Education if she will provide an update on the building project for a school (details supplied). [49652/22]

Amharc ar fhreagra

Freagraí scríofa

The school to which the Deputy refers was granted approval under the Department's Additional School Accommodation (ASA) Scheme 2020.

The approval was for the provision of 4 General Classrooms, 2 SET Rooms, a 2-Class SEN Base, 1 Textile Room, 2 Science Labs, 1 Prep Area, 2 DCG Rooms, 1 Art Room, 1 Art Project Room Storage and the removal of 2 temporary accommodation units.

Subsequent to the original approval, a change of scope request was received by my Department, and this is currently being reviewed by Schools Capital Appraisal Section (SCAS).

A decision on this request will issue from my Department as soon as possible.