Education Policy

Dáil Éireann Debate, Thursday - 24 November 2022

Thursday, 24 November 2022

Ceisteanna (230)

Bernard Durkan

Ceist:

230. Deputy Bernard J. Durkan asked the Minister for Education the degree to which she and her Department continue to assess the educational needs at primary and second level in Prosperous, County Kildare, with particular reference to the completion of promised or existing projects arising from the demographics in the area; if she is satisfied regarding the adequacy of school accommodation in the area; and if she will make a statement on the matter. [58668/22]

Amharc ar fhreagra

Freagraí scríofa

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

There are currently no issues identified which will impact on progression of projects in Prosperous. Please see attached table showing details on all building projects ongoing in Prosperous. The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages. My Department will continue to review all School Planning Areas with regard to any demographic changes that may result in the need for further additional school accommodation.

Roll_Number

School_Planning_Area

School_Name

Total_Project_Brief

Programme_List

12998C

Prosperous_Clane

S N CIANOG NAOFA

1x80m2 Mainstream, 1x SET room

Additional School Accommodation Scheme

13902O

Prosperous_Clane

HEWETSONS N S

6 classrooms Plus 1 SEN Base

Large Scale Capital Programme

16845U

Prosperous_Clane

RATHCOFFEY N S

2 classroom 183m2 and conversion of existing to multi-purpose room

Additional School Accommodation Scheme

18096P

Prosperous_Clane

S N COILL DUBH

2x80m2 Mainstream+ ensuite toilet & 2 x ASD Unit Classroom

Additional School Accommodation Scheme

18096P

Prosperous_Clane

S N COILL DUBH

Reconfiguration works to existing MCR for 2 x interim SEN classes

Additional School Accommodation Scheme

19796C

Prosperous_Clane

ST PATRICKS BNS

24 Classroom School

Large Scale Capital Programme

20505S

Prosperous_Clane

Scoil Mhuire Allenwood National School

3 x 80m2, 2 x SEN base & reconfiguration to existing smaller MCR to create later MCRS

Additional School Accommodation Scheme

70720G

Prosperous_Clane

St Farnan's Post Primary School

a new school building to increase capacity to LTPE 1000, existing PE hall to be refurbished

Large Scale Capital Programme

91372D

Prosperous_Clane

Scoil Mhuire Community School

2xScience labs, 5x General classrooms

Additional School Accommodation Scheme

Barr