Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Thursday, 24 Nov 2022

Written Answers Nos. 229-237

Education Policy

Ceisteanna (229)

Bernard Durkan

Ceist:

229. Deputy Bernard J. Durkan asked the Minister for Education the degree to which she and her Department continue to assess the educational needs at primary and second level in Clane, County Kildare, with particular reference to the completion of promised or existing projects arising from the demographics in the area; if she is satisfied regarding the adequacy of school accommodation in the area; and if she will make a statement on the matter. [58667/22]

Amharc ar fhreagra

Freagraí scríofa

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

There are currently no issues identified which will impact on progression of projects in Clane. Please see attached table showing details on all building projects ongoing in Clane. The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages. My Department will continue to review all School Planning Areas with regard to any demographic changes that may result in the need for further additional school accommodation.

Roll_Number

School_Planning_Area

School_Name

Total_Project_Brief

Programme_List

12998C

Prosperous_Clane

S N CIANOG NAOFA

1x80m2 Mainstream, 1x SET room

Additional School Accommodation Scheme

13902O

Prosperous_Clane

HEWETSONS N S

6 classrooms Plus 1 SEN Base

Large Scale Capital Programme

16845U

Prosperous_Clane

RATHCOFFEY N S

2 classroom 183m2 and conversion of existing to multi-purpose room

Additional School Accommodation Scheme

18096P

Prosperous_Clane

S N COILL DUBH

2x80m2 Mainstream+ ensuite toilet  & 2 x ASD Unit Classroom

Additional School Accommodation Scheme

18096P

Prosperous_Clane

S N COILL DUBH

Reconfiguration works to existing MCR for 2 x interim SEN classes

Additional School Accommodation Scheme

19796C

Prosperous_Clane

ST PATRICKS BNS

24 Classroom School

Large Scale Capital Programme

20505S

Prosperous_Clane

Scoil Mhuire Allenwood National School

3 x 80m2, 2 x SEN base & reconfiguration to existing smaller MCR to create later MCRS

Additional School Accommodation Scheme

70720G

Prosperous_Clane

St Farnan's Post Primary School

a new school building to increase capacity to LTPE 1000, existing PE hall to be refurbished

Large Scale Capital Programme

91372D

Prosperous_Clane

Scoil Mhuire Community School

2xScience labs, 5x General classrooms

Additional School Accommodation Scheme

Education Policy

Ceisteanna (230)

Bernard Durkan

Ceist:

230. Deputy Bernard J. Durkan asked the Minister for Education the degree to which she and her Department continue to assess the educational needs at primary and second level in Prosperous, County Kildare, with particular reference to the completion of promised or existing projects arising from the demographics in the area; if she is satisfied regarding the adequacy of school accommodation in the area; and if she will make a statement on the matter. [58668/22]

Amharc ar fhreagra

Freagraí scríofa

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

There are currently no issues identified which will impact on progression of projects in Prosperous. Please see attached table showing details on all building projects ongoing in Prosperous. The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages. My Department will continue to review all School Planning Areas with regard to any demographic changes that may result in the need for further additional school accommodation.

Roll_Number

School_Planning_Area

School_Name

Total_Project_Brief

Programme_List

12998C

Prosperous_Clane

S N CIANOG NAOFA

1x80m2 Mainstream, 1x SET room

Additional School Accommodation Scheme

13902O

Prosperous_Clane

HEWETSONS N S

6 classrooms Plus 1 SEN Base

Large Scale Capital Programme

16845U

Prosperous_Clane

RATHCOFFEY N S

2 classroom 183m2 and conversion of existing to multi-purpose room

Additional School Accommodation Scheme

18096P

Prosperous_Clane

S N COILL DUBH

2x80m2 Mainstream+ ensuite toilet & 2 x ASD Unit Classroom

Additional School Accommodation Scheme

18096P

Prosperous_Clane

S N COILL DUBH

Reconfiguration works to existing MCR for 2 x interim SEN classes

Additional School Accommodation Scheme

19796C

Prosperous_Clane

ST PATRICKS BNS

24 Classroom School

Large Scale Capital Programme

20505S

Prosperous_Clane

Scoil Mhuire Allenwood National School

3 x 80m2, 2 x SEN base & reconfiguration to existing smaller MCR to create later MCRS

Additional School Accommodation Scheme

70720G

Prosperous_Clane

St Farnan's Post Primary School

a new school building to increase capacity to LTPE 1000, existing PE hall to be refurbished

Large Scale Capital Programme

91372D

Prosperous_Clane

Scoil Mhuire Community School

2xScience labs, 5x General classrooms

Additional School Accommodation Scheme

Education Policy

Ceisteanna (231)

Bernard Durkan

Ceist:

231. Deputy Bernard J. Durkan asked the Minister for Education the degree to which she and her Department continue to assess the educational needs at primary and second level in Sallins, County Kildare, with particular reference to the completion of promised or existing projects arising from the demographics in the area; if she is satisfied regarding the adequacy of school accommodation in the area; and if she will make a statement on the matter. [58669/22]

Amharc ar fhreagra

Freagraí scríofa

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

With regard to the Sallins School Planning Area - there are currently no projects in progress for schools at primary or post-primary level in Sallins.

The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages. My Department will continue to review all School Planning Areas, including Sallins with regard to any demographic changes that may result in the need for further additional school accommodation in the future.

Education Policy

Ceisteanna (232)

Bernard Durkan

Ceist:

232. Deputy Bernard J. Durkan asked the Minister for Education the degree to which she and her Department continue to assess the educational needs at primary and second level in Kill, County Kildare, with particular reference to the completion of promised or existing projects arising from the demographics in the area; if she is satisfied regarding the adequacy of school accommodation in the area; and if she will make a statement on the matter. [58670/22]

Amharc ar fhreagra

Freagraí scríofa

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

With regard to the Kill School Planning Area - there are currently no projects in progress for schools at primary or post-primary level in Kill.

The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages. My Department will continue to review all School Planning Areas including Kill Co. Kildare with regard to any demographic changes that may result in the need for further additional school accommodation.

Education Policy

Ceisteanna (233)

Bernard Durkan

Ceist:

233. Deputy Bernard J. Durkan asked the Minister for Education the degree to which she and her Department continue to assess the educational needs at primary and second level in Celbridge, County Kildare, with particular reference to the completion of promised or existing projects arising from the demographics in the area; if she is satisfied regarding the adequacy of school accommodation; and if she will make a statement on the matter. [58671/22]

Amharc ar fhreagra

Freagraí scríofa

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

There are currently no issues identified which will impact on progression of projects in Celbridge. Please see attached table showing a list of all building projects ongoing in Celbridge.

The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages. My Department will continue to review all School Planning Areas with regard to any demographic changes that may result in the need for further additional school accommodation.

Roll_Number

School_Planning_Area

School_Name

Total_Project_Brief

Programme_List

18644U

Celbridge

STRAFFAN N S

4 x 80m2 mainstream classrooms & wc for assister users & stairs

Additional School Accommodation Scheme

18644U

Celbridge

STRAFFAN N S

2 SEN Class Base Unit & 1 x 100m2 Interim prefab wef Sept 21

Additional School Accommodation Scheme

18988G

Celbridge

ST RAPHAELS SPECIAL SCH

Proposal for 25 classroom school

Large Scale Capital Programme

20257C

Celbridge

Scoil Naomh Padraig

16 Classroom School+ SEN Base

Large Scale Capital Programme

61661P

Celbridge

Salesian College

2 Classroom Base SNU + 4 resource rooms

Additional School Accommodation Scheme

91614B

Celbridge

Celbridge Community School

Proposed 1,000 pupil + 4 SEN Base

Large Scale Capital Programme

91614B

Celbridge

Celbridge Community School

Provide Classrooms

Additional School Accommodation Scheme

Education Policy

Ceisteanna (234)

Bernard Durkan

Ceist:

234. Deputy Bernard J. Durkan asked the Minister for Education the extent to which she continues to monitor the educational requirements in Leixlip, County Kildare at primary and secondary level, given the population increases in the area; if she is satisfied that all eventualities are being catered for; and if she will make a statement on the matter. [58672/22]

Amharc ar fhreagra

Freagraí scríofa

I wish to advise the Deputy that requirements for additional school places is kept under on-going review in the context of available information on population, enrolments and residential development activity.

In order to plan for school provision and analyse the relevant demographic data, my Department divides the country into 314 school planning areas and uses a Geographical Information System, using data from a range of sources, including Child Benefit and school enrolment data, to identify where the pressure for school places across the country will arise and where additional school accommodation is needed at primary and post-primary level.

The 2022 demographic exercise indicates that 85% of the 314 school planning areas at primary level show static or decreasing enrolments for the period to 2026 compared with 2021. At post-primary level some 74% of school planning areas are anticipated to have increased enrolments for the period to 2029, with most expected to reach a peak within the next two or three years.Where demographic data indicates that additional provision is required, the delivery of such additional provision is dependent on the particular circumstances of each case and may, be provided through:

- Utilising existing unused capacity within a school or schools,

- Extending the capacity of a school or schools,

- Provision of a new school or schools. The most recent projections for the Leixlip School Planning Area indicate an increase in requirements at both primary and post primary level in the short term followed by a projected reduction in enrolments thereafter. The Department will continue to liaise with the Local Authority in Kildare in respect of their County Development Plan and any associated Local Area Plans with a view to identifying any potential long-term school accommodation requirements across school planning areas including in Leixlip.There are three capital projects planned in the Leixlip school planning area and when completed, will cater for the demand for school places in the area:

Leixlip Primary School (Roll Number 20256D) Brief: 8 Classroom School. Project Brief Stage (this includes determining the project brief and schedule of accommodation).

Scoil Bhride (Roll Number 19407L) Brief: 2 x Special Education Needs Base. Stage 1 (Stage 1 is the Preliminary Design Stage where the Design Team in conjunction with the school authorities, will analyse all the constraints of the site, develop a preferred design option and ensure that the preferred option is the best option for the delivery of the brief).

Confey Community College (Roll Number 70691C) Brief: 1 x Special Education Needs Base. Stage 1 (Stage 1 is the Preliminary Design Stage where the Design Team in conjunction with the school authorities, will analyse all the constraints of the site, develop a preferred design option and ensure that the preferred option is the best option for the delivery of the brief).

Schools Building Projects

Ceisteanna (235)

Bernard Durkan

Ceist:

235. Deputy Bernard J. Durkan asked the Minister for Education if official approval and a building formulation report will be provided to the school authorities of a school (details supplied) to enable the school building project to progress to tender stage as soon as possible given its current accommodation and expectations for future enrolments; and if she will make a statement on the matter. [58673/22]

Amharc ar fhreagra

Freagraí scríofa

I wish to advise the Deputy that my Department has informed the school patron that the accommodation brief for the building project in question is currently being formulated and that my Department will be in further contact with the patron when this process has been completed.

School Staff

Ceisteanna (236, 237)

Bernard Durkan

Ceist:

236. Deputy Bernard J. Durkan asked the Minister for Education the number of teachers currently employed at primary level throughout the country; the extent to which this meets requirements at the present time; the ongoing efforts being made to address shortages in respect of teachers for permanent and or temporary positions; and if she will make a statement on the matter. [58674/22]

Amharc ar fhreagra

Bernard Durkan

Ceist:

237. Deputy Bernard J. Durkan asked the Minister for Education the number of teachers currently employed at second level throughout the country; the extent to which this meets requirements at the present time; the ongoing efforts being made to address shortages in respect of teachers for permanent and or temporary positions; and if she will make a statement on the matter. [58675/22]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 236 and 237 together.

Teacher allocations to all schools are approved annually by my Department in accordance with established rules based on recognised pupil enrolment on the previous 30 September. The criteria for the allocation of posts are communicated to school managements annually and are available on the Department website.

As of end of October, there were approximately 22,200 contracted paid post-primary school teachers and some 3,700 substitute post-primary teachers employed (figures exclude teachers employed in ETB schools) and approximately 42,400 contracted paid primary school teachers and some 6,800 substitute primary teachers.

I am aware that some schools are currently experiencing difficulties in recruiting teachers.

My Department runs a comprehensive programme of work to support the supply of teachers.

Newly qualified teachers (NQTs) represent an additional source of supply for substitute and full-time posts in 2022/23 with over 3,600 primary and post-primary NQTs registered with the Teaching Council this year.

The Department of Education runs a comprehensive programme of work to support the supply of teachers.

Higher Education Institutions have developed new 4-year Initial Teacher Education undergraduate programmes in a number of post-primary priority subject areas including Irish, mathematics, computer science and modern foreign languages.

In addition, the Department funds upskilling programmes for post primary teachers in mathematics, physics, and Spanish. Approximately 170 teachers are expected to graduate from these programmes this year and over 300 teachers in 2023.

The Department also has a scheme to allow post-primary schools to share teachers, the aim of which is to recruit teachers in high demand subjects and give teachers a full time teaching contract. I would strongly urge schools to explore this option as a way of meeting teacher demand.

In May 2021, the Department published an updated technical report “Developing a Teacher Demand and Supply Model for Ireland 2020-2038”, which includes projections of teacher supply and demand at a general level to 2038.

The report projects a decrease in demand for primary teachers to 2036 while at post-primary level the downward trend in demand starts from 2024. The report’s projections are based on high level demographics and do not take account of policy measures that affect teachers demand or supply.

Work is ongoing to produce projections of post-primary teacher demand and supply on a subject level basis. It is intended to publish a draft report, for consultation with the education stakeholders, in the coming weeks.

The Irish Primary Principals’ Network (IPPN) has developed a portal for the recruitment of teachers to long-term teaching positions which I understand will be available in the coming weeks.

IPPN also operates Sub Seeker, a service matching primary and post-primary teachers with substitute vacancies. Almost 12,000 teachers have registered with Sub Seeker to date.

Significant additional posts have been allocated to the primary substitute teacher supply panels in areas where significant challenges in sourcing substitution continue, bringing the total to 610 posts on 151 panels, covering more than 2,840 schools.

For the current school year, job sharing teachers may be employed to work in a substitute capacity and the limit on substitute work applying to teachers on career break has been suspended.

3rd and 4th year student teachers can now register with the Teaching Council and more than 2,100 student teachers have applied for registration. Once registered, student teachers can be employed by a school to cover substitutable vacancies.

At post-primary level the Department has recently put in place a scheme that allows teachers teach additional hours in their subject area over the usual 22-hour weekly limit, up to a maximum of 20 additional hours per term.

Furthermore, retired teachers who maintain their registration, can provide substitute cover and the Department has agreed a waiver of abatement with the Department of Public Expenditure and Reform for such teachers for up to 50 days in each of the three calendar years, 2021 to 2023 inclusive.

These measures are underpinned by the Teaching Transforms campaign, which promotes the teaching profession and encourages students to follow a career in teaching. The campaign is supported by a dedicated webpage on Gov.ie entitled teachingtransforms.

The Department of Education will continue, with the cooperation of the education partners, to develop and implement measures to address challenges faced by schools and to continue to support the supply of teachers.

Question No. 237 answered with Question No. 236.
Barr
Roinn