Schools Refurbishment

Dáil Éireann Debate, Wednesday - 7 December 2022

Wednesday, 7 December 2022

Ceisteanna (61)

Pauline Tully

Ceist:

61. Deputy Pauline Tully asked the Minister for Education the timeframe for the refurbishment works on a school (details supplied) to be completed; the estimated cost of these works; and if she will make a statement on the matter. [61310/22]

Amharc ar fhreagra

Freagraí scríofa

The project referred to by the deputy has been devolved for delivery to Cavan and Monaghan Education and Training Board (CMETB). The project consists of an extension & major refurbishment of existing buildings to provide for 4 Mainstream classrooms and 2 SET rooms.

The project is currently nearing completion of Stage 3 of the architectural planning process. The tender submissions are currently under review by CMETB. While at this early stage it is not possible to provide a timeline for completion of the project, CMETB will be engaging directly with the school authority to keep it informed of progress.

Barr
Roinn