School Accommodation

Dáil Éireann Debate, Tuesday - 31 January 2023

Tuesday, 31 January 2023

Ceisteanna (462)

Patrick Costello

Ceist:

462. Deputy Patrick Costello asked the Minister for Education the expected timeline for completion of the current renovation works at a school (details supplied). [4684/23]

Amharc ar fhreagra

Freagraí scríofa

The project referred to by the Deputy is at Architectural Planning Stage 3 - Tender Action and Award.  A tender process can take between 8-12 months to complete, subject to no issues arising.

My Department has a large pipeline of projects for delivery under the school building programme, including the project referred to by the Deputy.  The main elements of this pipeline currently involve in excess of 1,300  school building projects for delivery under my Department's Large Scale and Additional Accommodation Scheme.  These projects are currently in progress across the various stages of planning, design, tender and construction, most of which are expected to be either under construction or completed in the period up to 2025.

During January, my Department will be assessing overall requirements for 2023 and associated work  programme and will update individual schools of same in due course. 