Dáil Éireann Debate, Thursday - 2 February 2023

Thursday, 2 February 2023

Ceisteanna (237)

Pauline Tully

Ceist:

237. Deputy Pauline Tully asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the timeframe for the completion of the refurbishment works on Bailieborough Garda station; the estimated cost of these works; and if he will make a statement on the matter. [5301/23]

Amharc ar fhreagra

Freagraí scríofa

The project for a new Garda Station at Bailieborough, Co. Cavan includes conservation of the existing former National Irish Bank building and the construction of a new three storey over basement building to the rear on a site of circa 0.15 hectares located on the town’s main street.  The  construction contract value for the works is €10,976,632 excluding VAT.

Construction work commenced in January 2022.  The construction programme is projected to be completed in Quarter 4 2023.