Dáil Éireann Debate, Tuesday - 28 March 2023

Tuesday, 28 March 2023

Ceisteanna (365, 400)

Bríd Smith

Ceist:

365. Deputy Bríd Smith asked the Minister for Education if she will clarify why the procurement process for a contractor for a school (details supplied) has been halted; if she will acknowledge the need for an ETSS in this area to accommodate the significant number of children who want to continue their education in an ETSS; if she will reconsider the stoppage on the procurement process and allow this necessary secondary school be progressed as soon as possible; and if she will make a statement on the matter. [14659/23]

Amharc ar fhreagra

Joan Collins

Ceist:

400. Deputy Joan Collins asked the Minister for Education the reason the procurement process has been halted for a contractor for a school (details supplied). [14939/23]

Amharc ar fhreagra

Freagraí scríofa

I propose to take Questions Nos. 365 and 400 together.

The permanent school building project for the site referred to by the Deputies is a campus project to deliver a 1,000 pupil post-primary school and accommodation, including four classrooms, for children with special educational needs and a 16 classroom primary school and accommodation, including two classrooms, for children with special educational needs. The campus project is being delivered under my Department's Design and Build programme.

My Department's Planning and Building Unit is currently assessing its work programme and priorities for 2023 in the context of its available funding. My Department's published NDP allocation for 2023 is €860 million. Key priorities for my Department's work programme include continuing strong delivery to support the operation of the school system with particular regard to planning ahead for the 2023/24 school year and beyond and also with particular regard to supporting special needs provision.

High construction inflation remains a continuing feature of the construction sector for 2023. As part of its planning ahead for the remainder of 2023, my Department is engaging with the Department of Public Expenditure, NDP Delivery and Reform in relation to capital funding pressures in order to continue to adequately support the operation of the school system with rollout of school building projects to construction in 2023. I am conscious of the numerous pressures facing the Department and their need to manage these.

I want to reassure the Deputies and the relevant school communities that school building projects that are currently on hold due to capital funding pressures will be progressed and delivered – it is a question of timing.

We will be providing an update to individual schools when our engagement with the Department of Public Expenditure, NDP Delivery and Reform concludes. In tandem with this, my Department’s Planning & Building Unit will also be updating Patron Bodies and School Management Bodies at that stage.

My Department will continue to liaise with the school's patron body in relation to the school's interim accommodation needs pending delivery of the permanent accommodation for the school.