School Accommodation

Dáil Éireann Debate, Tuesday - 18 April 2023

Tuesday, 18 April 2023

Ceisteanna (649)

Alan Kelly

Ceist:

649. Deputy Alan Kelly asked the Minister for Education if the temporary accommodation sanctioned for a school (details supplied) is on track to be in place for the new school year in September 2023; and if she will make a statement on the matter. [16609/23]

Amharc ar fhreagra

Freagraí scríofa

I can confirm to the Deputy that my Department approved a project for modular accommodation of 4 general classrooms and 1 ICT Room under the Additional School Accommodation (ASA) Scheme for the school referred to by the Deputy.

The project is currently being reviewed by my Department and the school authority will be advised directly on the outcome of this review. The current status of all projects are listed on a county by county basis at www.gov.ie and is updated on a regular basis to reflect their progress through the various stages of capital appraisal, site acquisition, design, tender and construction.

Barr
Roinn