655. Deputy Claire Kerrane asked the Minister for Rural and Community Development if she will provide a update on works (details supplied) under the small-scale capital works programme; the timeline for these works; when they are expected to conclude; and if she will make a statement on the matter. [18989/23]

Amharc ar fhreagra

Freagraí scríofa

The provision of library services, including the provision of library buildings, is primarily a matter for local authorities in their capacity as library authorities under the Local Government Act 2001. Accordingly, progress on the works in Ballaghaderreen Library, and the timeline for completing the project are, first and foremost, a matter for Roscommon County Council.

I am advised that Roscommon County Council published a tender in June 2022 seeking the services of a mechanical and electrical consultant for this project, but no responses were received. The council subsequently re- published the tender which resulted in the appointment of consultants in September 2022. The consultants are leading a multidisciplinary team that includes a conservation expert, and are providing expert advice in line with the requirements of the Section 57 Declaration under the Planning and Development Act, 2000.

I am further advised that in their assessment of the project, the consultants have now identified works that are required to the heating system. These works will involve the replacement of the existing heating system, with a new energy-efficient system, and enhancement to the insulation fabric of the building.

I understand that Roscommon County Council has now decided to adopt the recommendations of the consultants, given the age and inefficiency of the existing heating system, and the specification of works is being revised to include this. The revised specification is currently being finalised in preparation for publication of the tender in June 2023, and this will result in a revision to the timelines for delivery.

Roscommon County Council have informed my department that they expect to award the contract in August 2023, and the duration of the revised works including fit-out is now estimated at 28 weeks, which will result in the project being completed in Quarter 1 2024.

Roscommon County Council continues to provide a weekly mobile library service in Ballaghaderreen alongside services to local schools and preschools and attendance at community events. Due to the change in the duration of the works, the Council is exploring options for the provision of a temporary library building in the town while works are ongoing.

My department continues to engage with the Council to ensure that library services are maintained as far as possible in Ballaghaderreen and surrounding areas.