Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects

Dáil Éireann Debate, Tuesday - 30 May 2023

Tuesday, 30 May 2023

Ceisteanna (287)

James Lawless

Ceist:

287. Deputy James Lawless asked the Minister for Education if she will provide a timeline on the delivery of a new school building (details supplied) in County Meath; and if she will make a statement on the matter. [26133/23]

Amharc ar fhreagra

Freagraí scríofa

The school referred to by the Deputy is being delivered by my Department’s Design and Build programme which uses a professional external Project Management team to progress the project through the stages of architectural planning, tendering and construction.

The project proceeded to tender on 18th April 2023 as part of a bundle of projects which issued to a Framework of Design & Build Contractors.

The tender process currently takes approximately 8-10 months. Once a Contractor has been appointed, it is anticipated that construction would commence shortly thereafter.

Barr
Roinn