Schools Refurbishment

Dáil Éireann Debate, Tuesday - 30 May 2023

Tuesday, 30 May 2023

Ceisteanna (326)

Sorca Clarke

Ceist:

326. Deputy Sorca Clarke asked the Minister for Education when the refurbishment works at a school (details supplied) are expected to be completed; and the estimated cost for these works. [26339/23]

Amharc ar fhreagra

Freagraí scríofa

The project to which the Deputy refers has been devolved for delivery to Louth and Meath Education and Training Board (LMETB).

Works commenced onsite in December 2021, and providing that nothing unforeseen arises, it is expected to reach substantial completion in Q1 2024.

As this project is still ongoing, it is not possible to provide the costs which remain commercially sensitive until the Final Account is approved.