Schools Refurbishment

Dáil Éireann Debate, Tuesday - 30 May 2023

Tuesday, 30 May 2023

Ceisteanna (331)

Sorca Clarke

Ceist:

331. Deputy Sorca Clarke asked the Minister for Education when refurbishment works at a school (details supplied) will be completed; and the estimated cost for these works. [26344/23]

Amharc ar fhreagra

Freagraí scríofa

The Letter of Acceptance (LOA) for the major school building project referred to by the Deputy issued to the preferred tenderer on 31 May 2022 commencing the school building contract.

Works are progressing well on site and the school building is due for completion in Q4 2023.

There are no refurbishment works planned for the school's current accommodation under the Design and Build contract.