Hospital Facilities

Dáil Éireann Debate, Tuesday - 27 June 2023

Tuesday, 27 June 2023

Ceisteanna (641)

Seán Canney

Ceist:

641. Deputy Seán Canney asked the Minister for Health if he will consider the option of appointing a project delivery team to oversee the delivery of major projects including the new emergency department, maternity unit, paediatric unit, regional cancer centre, bedroom block and laboratories on the existing site at University Hospital Galway to ensure delivery is achieved in the shortest time possible; and if he will make a statement on the matter. [30641/23]

Amharc ar fhreagra

Freagraí scríofa

Design teams have already been appointed to deliver the new Emergency Department (ED), Women and Children’s block, replacement laboratories and cancer centre proposals at University Hospital Galway (UHG). At any one time there are multiple capital investment projects underway on the UHG campus involving different design teams and different works contractors. It is normal practice for there to be different design teams in place to deliver different projects on a single site. This is especially true for the three projects referenced above given the scale and complexity of these proposals.

Overall co-ordination for all works / projects on the campus is achieved through close working relationships locally between HSE Capital & Estates, Saolta Hospital Group and management at Galway University Hospitals.

Strategies to mitigate any potential disruption to services while delivering capital works projects on a live, and extremely busy, hospital site are developed in advance of construction works and during the project lifecycle as part of an overall risk assessment.