688. Deputy Pauline Tully asked the Minister for Education when refurbishment works at a school (details supplied) will be completed; and the estimated cost for these works. [38601/23]

Amharc ar fhreagra

Freagraí scríofa

The school to which the Deputy refers was approved funding for a large scale major building project. The project is devolved for delivery to Cavan & Monaghan Educational Training Board (CMETB).

I am pleased to advise that this project is at stage 4 of the architectural process.  Works commenced onsite in June 2023 and the Project Executive expect it to be practically completed towards the end of 2024. CMETB will continue to engage and communicate directly with the school community in relation to the progression of the project.

The cost of the project will not be finalised until the project reaches final account after practical completion.