225. Deputy Sorca Clarke asked the Minister for Education when refurbishment works to a school (details supplied) will be completed. [50545/23]

Amharc ar fhreagra

Freagraí scríofa

The large scale capital project for the school referred to by the Deputy is at Architectural Planning Stage 4 - Construction. The Project commenced on site in May 2023 with a contract duration of 18 months, subject to no issues arising, the expected completion date is Q4 2024.