Schools Building Projects

Dáil Éireann Debate, Wednesday - 17 January 2024

Wednesday, 17 January 2024

Ceisteanna (468)

Pearse Doherty

Ceist:

468. Deputy Pearse Doherty asked the Minister for Education the timeline for when approval for construction for a school (details supplied) will be granted for a three-room extension; and if she will make a statement on the matter. [56333/23]

Amharc ar fhreagra

Freagraí scríofa

The school to which the Deputy refers, was approved a project under my Department's Additional School Accommodation (ASA) scheme for the provision of  1 music room, 1 home economics room, 1 engineering room and ancillary.

The project was devolved for delivery to the school authority.

My Department has received a Stage 2b (post planning approval) report from the school.  This report is currently being reviewed from both a technical and cost perspective in accordance with the requirements of the Public Spending Code.

My Department will be in contact with the school directly once its review of this report has been completed in regards to the next stages to progress the project.

Barr