Schools Building Projects

Dáil Éireann Debate, Tuesday - 20 February 2024

Tuesday, 20 February 2024

Ceisteanna (292)

Emer Higgins

Ceist:

292. Deputy Emer Higgins asked the Minister for Education for an update on the new modular build for a school (details supplied); when the brief acceptance letter will be issued; and if she will make a statement on the matter. [7749/24]

Amharc ar fhreagra

Freagraí scríofa

I can confirm to the Deputy, that the school in question was granted initial approval for a significant modular accommodation project under my Department's Additional School Accommodation (ASA) scheme.

The Department has a significant modular accommodation programme in place to assist schools in the provision of additional capacity, including in respect of facilitating the establishment of special classes.

This programme involves the use of Project Management supports which is designed to enable the accommodation to be provided as quickly as possible and help ease the administrative workload for school authorities in relation to the management and delivery of projects.

The use of the Department’s Modular Accommodation Framework also assists in ensuring lead in periods for procurement of modular accommodation are minimised to the greatest extent possible.

I can confirm that the school in question was assigned a Project Manager under this programme and the project has progressed to viability report stage. The consideration of the accommodation requirements for this school forms part of the Planning and Building Unit’s overall assessment of its work programme and priorities in the context of available capital funding. It is not, therefore, possible to give an indication at this point in time of the timeframe for the provision of additional accommodation at the school.

I can only seek to assure you that we will advance this matter as quickly as possible.

Barr
Roinn