81. Deputy Martin Browne asked the Minister for Transport the reasons for the delay in providing the funding needed to allow for the continuation of work on designing the upgrade to the Cahir to Limerick Junction section of the N24 road project; if he is aware that the funding received for the project to date is diminishing and the remaining funding is needed immediately to quell concerns that, otherwise, this section of the project may stall; when the funding will be made available; and if he will make a statement on the matter. [22069/24]

Amharc ar fhreagra

Freagraí scríofa

As Minister for Transport, I have responsibility for overall policy and exchequer funding in relation to the National Roads Programme. Under the Roads Acts 1993-2015 and in line with the National Development Plan (NDP), the planning, design and construction of individual national roads is a matter for Transport Infrastructure Ireland (TII), in conjunction with the local authorities concerned. This is also subject to the Infrastructure Guidelines and the necessary statutory approvals. In this context, TII is best placed to advise you.

I can confirm that €650,000 was allocated for the N24 Cahir to Limerick Junction scheme in 2024. As with all national roads projects in the NDP, the delivery programme for this project will be kept under review for 2025 and considered in terms of the overall funding envelope available to TII.

Noting the above position, I have referred your question to TII for a direct reply updating you regarding the status of this project. Please advise my private office if you do not receive a reply within 10 working days.