241. Deputy Catherine Murphy asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the amount the OPW has spent to date on the construction of a new public sector data centre; and when this centre will open. [22379/24]

Amharc ar fhreagra

Freagraí scríofa

To date €28,323,757.06 has been spent on the construction of the new Public Sector Data Centre,

This Figure is inclusive of VAT. Substantial completion is scheduled for May 2025.