andMr. Mullen asked the Minister for Local Government the approximate time which elapses from the commencement of site development to the first handover to the Dublin Corporation of houses or flats built in the traditional manner.
Ceisteanna—Questions. Oral Answers. - Dublin Corporation Houses and Flats.
16.
The time which elapses between the commencement of site development and the first handover of houses or flats varies according to the size of the contract, working methods, site conditions, weather and availability of labour and materials. I understand that, for schemes completed by Dublin Corporation in recent years, the period has ranged from 16 to 20 months.