Written Answers. - Roscommon PO Engineering Headquarters.

255.

asked the Minister for Posts and Telegraphs if he has arranged for the appointment of a building contractor to complete engineering headquarters for his Department at Racecourse Road, Roscommon, which was commenced in December 1982; the expected completion date; and the overall revised cost of the completed project.

The Office of Public Works have advised that a contract for completion of the new area engineering headquarters at Racecourse Road, Roscommon, is expected to be placed within the next two weeks. The building should be completed six months after the contract is placed. The overall revised cost of the completed project, which includes cost of building and site, consultants' fees, furniture etc., is estimated at £500,000.