Written Answers. - Athlone Relief Road.

448.

asked the Minister for the Environment the reason for the delay in the issuing of the findings in relation to the compulsory purchase orders in connection with the Athlone relief road.

There has been no avoidable delay in dealing with this case which concerns an extensive road and bridge project and which involved the holding of a public local inquiry over four days into objections to five compulsory purchase orders for the acquisition of some 176 acres of land and an application for a bridge order for the construction of a new bridge over the Shannon at Clonbrusk, Athlone. I will give my decision on the proposals at the earliest possible date.