Figary Watersports Development Co. Ltd (FWD) were granted a foreshore lease in April 1993. The company proposed to construct a marina at the site but did not progress the project.
Following a request from the company for a meeting, I met with the promoters on 26 February 1998, to discuss their problems.
Following this meeting, the company commenced work on the project and were immediately requested to stop. The company did not accede to this request or to a further request that work should stop so that a report could be prepared by a consultant structural engineer on the stability of the structures already erected. Accordingly, on 15/16 April 1998, Prohibitory Notices were served on the chief executive officer of FWD and on the contractors.