Westmeath
|
1997
|
1998
|
1999
|
2000
|
2001
|
Total
|
Athlone Main Drainage Contract 1 Stage 2
|
|
|
£160,503.00203,796.77
|
|
|
£160,503.00203,796.77
|
Athlone Main Drainage West Bank
|
|
|
£2,017,101.002,561,189.95
|
£1,030,136.001,308,002.91
|
£2,000,000.002,539,476.16
|
£5,047,237.006,408,669.01
|
Kinnegad Sewerage
|
|
|
£112,195.00142,458.26
|
|
|
£112,195.00142,458.26
|
Moate SewerageTreatment Works
|
£1,196,043.001,518,661.34
|
£978,426.001,242,344.75
|
£576,268.00731,709.42
|
£359,833.00456,893.66
|
|
£3,450,306.004,380,984.91
|
Westmeath SludgeManagement Plan
|
|
|
|
£36,048.7745,772.50
|
|
£36,048.7745,772.50
|
|
£1,196,043.001,518,661.34
|
£978,426.001,242,344.75
|
£2,866,067.003,639,154.41
|
£1,426,017.771,810,669.06
|
£2,000,000.002,539,476.16
|
£8,466,553.7710,750,305.72
|
Kerry
|
1997
|
1998
|
1999
|
2000
|
2001
|
Total
|
Ballybunion Sewerage
|
|
|
£7,877.8910,002.86
|
|
|
£7,877.8910,002.86
|
Ballyheigue Sewerage
|
|
£263,736.00334,875.64
|
£231,915.00294,471.31
|
£50,305.9963,875.43
|
|
£545,956.99693,222.38
|
Caherciveen Sewerage
|
|
|
|
£396,372.48503,289.23
|
|
£396,372.48503,289.23
|
Dingle Sewerage
|
£1,020,124.001,295,290.29
|
|
|
|
|
£1,020,124.001,295,290.29
|
Farranfore Sewerage
|
|
|
|
£261,028.15331,437.38
|
|
£261,028.15331,437.38
|
Kenmare Sewerage
|
|
|
|
£806,598.571,024,168.92
|
|
£806,598.571,024,168.92
|
Killarney Sewerage
|
£2,095,417.002,660,630.76
|
£2,256,383.002,865,015.41
|
£423,515.00537,753.12
|
£322,226.00409,142.62
|
|
£5,097,541.006,472,541.91
|
Killarney SludgeTreatment Centre
|
£62,193.0078,968.82
|
£1,096,106.001,391,767.53
|
£64,937.0082,452.98
|
£712,020.40904,079.41
|
|
£1,935,256.402,457,268.74
|
Knightstown Sewerage
|
|
£1,079.001,370.05
|
|
|
|
£1,079.001,370.05
|
Rathmore Sewerage
|
|
|
£100,253.00127,295.05
|
£450,486.56571,999.94
|
|
£550,739.56699,294.99
|
Tralee Flood ReliefContract 1
|
|
|
£128,800.00163,542.26
|
|
|
£128,800.00163,542.26
|
Tralee Flood ReliefContract 2
|
|
|
£34,024.0043,201.57
|
|
|
£34,024.0043,201.57
|
Tralee Flood ReliefContract 3
|
|
|
£464,097.00589,281.63
|
|
|
£464,097.00589,281.63
|
Tralee Flood ReliefScheme, Stage 1, 4b
|
|
|
£103,358.00131,237.59
|
|
|
£103,358.00131,237.59
|
Tralee Sewerage
|
£2,776,790.303,525,796.38
|
£1,887,068.842,396,083.16
|
|
|
|
£4,663,859.145,921,879.54
|
Tralee SewerageContract 1
|
|
£145,663.00184,953.86
|
£37,382.0047,465.35
|
|
|
£183,045.00232,419.21
|
Waterville Sewerage
|
|
£1,762.002,237.28
|
|
|
|
£1,762.002,237.28
|
|
£5,954,524.307,560,686.24
|
£5,651,797.847,176,302.93
|
£1,596,158.892,026,703.72
|
£2,999,038.153,807,992.94
|
£0.000.00
|
£16,201,519.1820,571,685.83
|