Light Rail Project.

Dáil Éireann Debate, Thursday - 28 September 2006

Thursday, 28 September 2006

Ceisteanna (101)

John Perry

Ceist:

94 Mr. Perry asked the Minister for Transport if he has set a date for signing the railway order for the Luas Red Line Point Depot extension; and if he will make a statement on the matter. [29722/06]

Amharc ar fhreagra

Freagraí scríofa

I would refer the Deputy to my reply of yesterday to Dáil Question No. 1087 in the same matter: "The Public Inquiry into the Railway Procurement Agency's (RPA) application for a Railway Order for a Luas extension of the Red Line from Connolly Station to the Point Depot concluded on 2 June 2006 and the Inspector's report on that Inquiry was published on 6 August 2006. I am currently considering the Inspector's report and all other relevant documentation in relation to the RPA's application with a view to making a decision on this matter in due course."

Barr