407 Dr. Cowley asked the Minister for Transport if he will confirm an underspend €500 million for roads in the Border Midland Western region; and if he will make a statement on the matter. [41072/06]

Amharc ar fhreagra

Freagraí scríofa

The National Development Plan investment programme for national roads is being implemented as part of the Economic and Social Infrastructure Operational Programme 2000 to 2006 (ESIOP). The total investment originally envisaged in national roads in the case of the BMW region for the seven years of the ESIOP was €2,479.362 million. The most recent forecast for the final outturn figure for national roads investment in the region for the period 2000 – 2006 is €2012.531 million, which is €534.96 million less than the amount originally envisaged.

At the start of the ESIOP, a relatively small number of major road projects in the BMW region had progressed through the planning, design and public procurement processes. The NRA provided grant assistance towards the acceleration of this work. As a result there was an intensification of planning and design activity on major road projects, resulting in a sharp upturn in the number of projects arriving at the construction stage, and a corresponding increase in the level of spending on national roads in the region since the beginning of 2004.

Construction work on a number of the projects will continue into the period after 2006. There is no question of an "underspend" or a loss of funding in respect of national roads in the BMW region. The position is that, at an early point after 2006 the total level of investment which had originally been envisaged for the seven year period from the start of 2000 to the end of 2006 will be reached and surpassed.

The major pick-up in road building activity in the BMW region has been acknowledged at the ESIOP Monitoring Committee.

Richard Bruton

Ceist:

408 Mr. Bruton asked the Minister for Transport the cost of the projects listed in his reply to Parliamentary Question No. 136 of 16 November 2006; and the cost of the projects completed in 2002 and 2003 with their locations and the kilometres of road in each case. [41120/06]

Amharc ar fhreagra

The costs of the projects listed in the reply to Parliamentary Question No. 136 of 16 November 2006 are listed in Table 1. The costs of the projects completed in 2002 and 2003, together with their locations, length and costs are set out in Table 2. All of this information has been sourced directly from the National Roads Authority who have overall responsibility for the planning design and implementation of the national roads programme under the Roads Act 1993.

Table 1

Route

Scheme

Outturn

€ million

2004

M7

Monasterevin Bypass

132.840

N8

Cashel Bypass

48.607

N11

Wyattville Interchange

45.000

N26

Ballina/Bohola Bypass

21.462

2005

M1

Dundalk Bypass

24.043

M4

Kilcock/Enfield/Kinnegad

231.488

N4

McNeads Bridge/Kinnegad

27.000

N4

Loughrea Bypass

21.700

N4

Sligo Inner Relief Road

74.276

N21

Ballcarthy Tralee

13.195

N22

Gortalea to Farrenfore

19.543

2006

N2

Ashbourne Bypass

182.000

N7

Naas Road Upgrade

229.280

N8

Fermoy/Rathcormac Bypass

133.100

N15

Ballyshannon/Bundoran Bypass

79.540

N21

Castleisland/Abbeyfeale

34.052

N25

Kinsale Road Interchange

48.130

N30

Enniscorthy/Clonroche

18.540

N55

Cavan Bypass

16.450

N8/73

Mitchelstown Bypass

25.140

Table 2

Route

Scheme

Kms

Road Type

Outturn

€ million

2002

N4

Enfield Relief Route

2.6

SC

13.253

N9

Grannagh to Waterford

0.5

DC

31.925

N15

Bunduff/Downes River

5.5

SC

2.476

N17

Knock/Claremorris (Phase 1+2)

16

SC

69.476

N18

Newmarket-on-Fergus Bypass

5.7

DC

48.683

N22

Bealagrellagh/Gortalea

3.5

WS

8.707

N24

Piltown/Fiddown

9.3

SC

35.083

N25

Carnaross

7.8

SC

26.796

2003

M1

Drogheda Bypass

22

M

262.393

M1

Lissenhall to Balbriggan

10

M

72.000

M1

Cloghran to Lissenhall

6.5

M

158.294

M7

Kildare Bypass

13

M

160.790

N8

Watergrasshill Bypass

10

DC

124.994

N11

Glen-of-the-Downs

5.5

DC

97.115

N18/19

Hurlers Cross

9.4

DC

104.264

N25

Youghal Bypass

6.2

SC

47.970

N71

Skibbereen Relief Road

1.2

SC

11.500

SC = Single Carriageway.

DC = Dual Carriageway.

M = Motorway.

WS = Wide Single Carriageway.

Barr