108 Deputy Ciarán Lynch asked the Tánaiste and Minister for Education and Skills if, given that new construction tenders are being sought, funds have been ringfenced for the completion of a school (details supplied) in County Cork; and if she will make a statement on the matter. [43170/10]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy will be aware, the project to which he refers encountered delays in securing planning permission and land transfers. These problems were compounded by certain issues that subsequently arose with the preferred bidder and which resulted in a recent decision to re-tender the project.

It is envisaged that the project will be re-tendered shortly. Subject to no issues arising, it is anticipated that it will progress to construction in early 2011.