307. Deputy Darren O'Rourke asked the Minister for Education for an update on the phase 2 build at a school (details supplied); and if she will make a statement on the matter. [10333/24]

Amharc ar fhreagra

Freagraí scríofa

The Major Building Project for the school referred to by the Deputy is currently at an advanced stage of architectural planning -Stage 2(b) – Detailed Design, where the design team secure all statutory approvals and prepare the suite of tender documents.

A revised planning permission is required as the original grant of planning permission for phase 2 of the major project has expired. In line with Climate 2030 and 2040 targets, my Department have requested the design team to include additional decarbonisation features in their design. The Design Team are preparing that revision to include in their application for planning permission to the Local Authority.

Once the statutory approvals have been secured, the design team can complete their Stage 2(b) documentation for review by my Department. Upon receipt, review and approval of the Stage 2(b) submission, my Department will update the School Authorities and the design team with regards to the further progression of the project.