Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 17 May 2016

Tuesday, 17 May 2016

Ceisteanna (263)

Colm Brophy

Ceist:

263. Deputy Colm Brophy asked the Minister for Education and Skills to set out the status of the progression of a new school build (details supplied) scheduled to be constructed in 2015; the reason for the delay; and if he will make a statement on the matter. [9536/16]

Amharc ar fhreagra

Freagraí scríofa

My Department is currently in the process of securing the site for the school building project to which the Deputy refers.

In tandem with the site acquisition process, the design work for the school has been advanced so the application for planning permission can be submitted as the site acquisition is closed.

Once the site has been acquired and planning permission secured, the project will then be progressed to tender and construction stages.