Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 28 June 2016

Tuesday, 28 June 2016

Ceisteanna (144)

Shane Cassells

Ceist:

144. Deputy Shane Cassells asked the Minister for Education and Skills the status of the planned construction of a school (details supplied) which is included in the school building programme for commencement in 2016; when will construction be completed; and if he will make a statement on the matter. [18387/16]

Amharc ar fhreagra

Freagraí scríofa

The major building project for the school referred to by the Deputy is at stage 2(a) of architectural planning, Developed Design Stage. Statutory approvals have been obtained for this project.

Upon successful completion of Stage 2(a), the project will progress to complete Stage 2(b), Detailed Design, which will include the preparation of Tender Documents for Contractors.

Until such time as the project has progressed to and completed tender stage and the appointment of a building contractor, it will not be possible to provide an indicative timeframe for the completion of the construction stage of the project.