Schools Building Projects

Dáil Éireann Debate, Tuesday - 27 September 2016

Tuesday, 27 September 2016

Ceisteanna (257)

Clare Daly

Ceist:

257. Deputy Clare Daly asked the Minister for Education and Skills if commencement of phase 2 of the construction of a school (details supplied) can be brought forward to ensure that students will not be sitting for exams in an overcrowded school building; and if he will make a statement on the matter. [26781/16]

Amharc ar fhreagra

Freagraí scríofa

The building project referred to by the Deputy is at an advanced stage of architectural planning Stage 2(b) - Detailed Design, which involves planning permission, fire certificate and disability access certificate and the completion of tender documents. All statutory approvals have been secured.

The second phase of the project provides for a new build to cater for an additional 650 pupils, a Special Needs Unit, a PE Hall with fitness suite and changing facilities and ancillary accommodation including a school library.

The Stage 2(b) report was recently submitted to my Department for review. Once the review is completed my Department will revert to the Design Team and ETB with regard to the timeline for further progression of the project.