The school to which the Deputy refers was allocated funding under the 2015 Additional Accommodation Scheme to provide a library, Kitchen & breakfast area, 8 learning support rooms and toilets.
The delivery of the project has been devolved to the school authority. The progression of the project is now, therefore, a matter for the Board of Management.
It is understood that Planning permission has recently been received and the Design Team is currently preparing the applications in respect of a Fire Cert and a Disability Access Cert. The project will then proceed to tender and construction stages. It is expected that construction will commence in 2017.
My Department recently received an application for an uplift in Design Team fees. This is currently being examined. This request does not impact the project progressing as outlined.