Road Safety

Dáil Éireann Debate, Wednesday - 10 May 2017

Wednesday, 10 May 2017

Ceisteanna (125)

Micheál Martin

Ceist:

125. Deputy Micheál Martin asked the Minister for Education and Skills the reason his Department has delayed for over 12 months in carrying out the road safety audit which is required for Cork County Council's roads department to install a pedestrian crossing for a school (details supplied); when this audit will be carried out; and if he will make a statement on the matter. [22299/17]

Amharc ar fhreagra

Freagraí scríofa

The school to which the Deputy refers was delivered under a Public Works Design & Build Contract which places the responsibility on the Contractor to submit the final compliance documents to the local authority.

Stage 1 and stage 2 Road Safety Audits were undertaken as part of the planning process.

My officials have sought clarification from the Contractors design team on the status of the Stage 3 Road Safety Audit. My officials will follow up with the Contractor to ensure that the Councils requirements are met as quickly as possible.