111. Deputy Michael McGrath asked the Minister for Education and Skills to outline the timeframe for the delivery of the planned education campus at Ballinrea, Carrigaline, County Cork; when he expects the project to go to tender, the commencement of construction and the occupancy of the three new school buildings; if the capital funding is in place for the delivery of this project; and if he will make a statement on the matter. [22530/17]

Amharc ar fhreagra

Freagraí scríofa

The delivery of the new education campus at Ballinrea, Carrigaline has been devolved to the Cork Education & Training Board (CETB).

Documentation to pre-qualify Contractors is currently being prepared by the CETB's Design Team. In addition, the Public Spending Code requires that a Cost Benefit Analysis be carried out for projects of the scale involved for the Carrigaline Campus. This work is also underway.

As soon as contractors are pre-qualified and tender documents completed, the project will then be considered for progression to tender and construction stage.