Schools Building Projects Status

Dáil Éireann Debate, Thursday - 26 October 2017

Thursday, 26 October 2017

Ceisteanna (101)

James Browne

Ceist:

101. Deputy James Browne asked the Minister for Education and Skills the proposed timeframe for development of a new school (details supplied) in County Wexford once the tender process is closed; and if he will make a statement on the matter. [45523/17]

Amharc ar fhreagra

Freagraí scríofa

In July 2017 the Stage 2b (Detailed Design) for this project was approved, pending the completion of the process to carry out a short-listing of suitably qualified building contractors and sub-contractors. The relevant short-listing contract notices were posted to the Official Journal of the European Community (OJEU) and the Government's E-tenders website on 27th September and 8th October respectively.

My Department anticipates that, following the tender process to appoint a Building Contractor, this project will go on site and commence construction in the first half of 2018.