464. Deputy Niall Collins asked the Minister for Rural and Community Development the level of RAPID programme funding on an annual basis in each of the years 2010 to 2016; the allocations for 2017 and 2018, in tabular form; and if he will make a statement on the matter. [50948/17]

Amharc ar fhreagra

Freagraí scríofa

RAPID (Revitalising Areas by Planning, Investment and Development) is aimed at funding projects which will enhance the lives of residents in disadvantaged urban areas and provincial towns. The current RAPID programme is managed locally by the Local Community Development Committees, with support from Local Authorities.

The first table that follows sets out funding provided under RAPID from 2010 to 2016.

The second table provides the allocation for 2017 and the indicative allocation for 2018. The total allocation in 2017 is €5 million. Each Local Authority administrative area received an allocation of €64,500 for RAPID for 2017, with an additional €2.5 million ring fenced for the Dublin North East Inner City area. In addition, €0.5 million is available to honour legacy commitments. These include my Department’s contractual commitments under previous RAPID projects, mainly under the Sports Capital Scheme.

Year

Outturn €'000s

2010

6,067

2011

2,269

2012

3,062

2013

261

2014

170

2015

317

2016

32

Year

Allocation €'000s

2017

5,000

2018

5,000 indicative