Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Data

Dáil Éireann Debate, Tuesday - 27 March 2018

Tuesday, 27 March 2018

Ceisteanna (256)

Thomas Byrne

Ceist:

256. Deputy Thomas Byrne asked the Minister for Education and Skills the number of school building projects that have been required to apply to local authorities for an extension of duration of planning permission due to delays; and the detail of each. [13758/18]

Amharc ar fhreagra

Freagraí scríofa

Seven major school building projects at Architectural Planning Stage have been required to apply to local authorities for an extension of duration of planning permission due to delays. The detail of each project are listed in the attached spreadsheet.

While it is a rare occurrence, it can happen that a project may experience delays following a grant of planning permission for a number of reasons. For example, a need to appoint a replacement architect or engineer on the design team, a legal challenge to a grant of planning permission, delays in securing a site or an extension to a site and changes sought in the brief by the school following the grant of planning permission. In some cases the delay can be attributable to an underperforming design team.

Included on the attached spreadsheet are two projects where an extension of planning permission has been sought and a decision is currently awaited from the Local Authority.

County

Roll No

School

Date Grant of PP extended from

Comment re delays

Cavan

19439B

Holy Family Special School

12/01/18

Changes to brief by the school following the grant of planning permission, need to appoint a replacement M&E engineer on the design team and delays while various decant proposals explored.

Longford

19429V

St. Christopher's Special School

17/07/17

Issues with Design Team

Donegal

19927O

Scoil Mhuire Stranorlar

12/05/17

Site acquired with conditional planning permission. Revised Brief Formulation Report necessary to take account of PP conditions imposed. Fire Safety Certificate appealed to An Bord Pleanála.

Cork

19415K

Scoil An athar Tadhg

09/01/18

Significant changes proposed by school to scope of project.

Cork

19993E

Gaelscoil An Ghoirt Álainn

08/12/16

Planning Permission appealed to An Bord Pleanála twice & a legal challenge to Planning Permission pending acquisition of site.

County

Roll No

School

Extension of PP application with Local Authority with effect from

Comment re delays

Meath

17705J

Whitecross

22/01/18

Full grant of Planning Permission received 13/1/14. Delays occurred due to school submitting various options for temporary decant and subsequent need to apply for statutory approvals for temporary decant off site.

Meath

18106P

Lismullen

19/02/18

Full grant of Planning Permission received 13/9/13. Issues with the Design Team contributed to delays.

Barr
Roinn