Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 24 April 2018

Tuesday, 24 April 2018

Ceisteanna (188)

Joan Burton

Ceist:

188. Deputy Joan Burton asked the Minister for Education and Skills further to Parliamentary Question No. 89 of 22 March 2018, if the minor issues that needed to be addressed by the design team have been dealt with; if the project will proceed to tender stage; and if he will make a statement on the matter. [17484/18]

Amharc ar fhreagra

Freagraí scríofa

The building project referred to by the Deputy is for a new 24 classroom school including a Special Needs Unit, with a floor area of approx. 4,748m2.

The project is currently at Stage 2B of Architectural Planning. The Stage 2B report was received into the Department and feedback provided to the Design Team.  The Design Team is currently working on the issues raised. 

A letter recently issued to the school outlining the projected timeframe for progression of this project to tender and construction stage and the steps involved.

Barr
Roinn