In April, 2015, my Department approved an all-in-devolved grant for the provision of 2 mainstream classrooms and a WC for assisted users for the school in question. The additional accommodation was to be provided on a stand-alone basis.
The project proceeded to tender without reverting to my Department as required under the terms and conditions of the Scheme. In addition, the Board of Management had tendered for an unapproved scope of works.
In June 2018 the Board was advised that it was required to revert to the original works approved. It is now a matter for the Board of Management to progress the project accordingly.