The major building project referred to by the Deputy is currently at Stage 2b – Detailed Design.
This project was authorised to commence the Pre-Qualification of Contractors in April 2018. The pre-qualification and shortlisting of suitable contractors normally takes between 8 and 12 weeks to complete.
The Design Team has confirmed that it is currently assessing expressions of interest applications. A pre-qualification report will be compiled and forwarded to the Department once this exercise is complete.
Thereafter, the tender process for the awarding of a construction contract will be carried out. This process takes between 7 and 8 months to complete.
In February 2018 my Department issued a letter to the school and its Design Team outlining the projected timeframe for the progression of this project to tender and construction stage and the steps involved.