Schools Building Projects Status

Dáil Éireann Debate, Thursday - 12 July 2018

Thursday, 12 July 2018

Ceisteanna (200)

Robert Troy

Ceist:

200. Deputy Robert Troy asked the Minister for Education and Skills the status of applications for works submitted by a school (details supplied). [32393/18]

Amharc ar fhreagra

Freagraí scríofa

The building project referred to by the Deputy is for a new 650 pupil Post Primary school on a Greenfield site. 

The project is currently at Stage 2A of Architectural Planning which includes developing the Design to a stage where it is fully cost planned and can be prepared to lodge for Statutory Approval. 

A Stage 2A meeting was held on June 28 2018 and the Design Team is required to follow up with an addendum submission. The project was authorised to proceed with the application for planning and statutory consent. Outline planning permission was secured as part of the Stage 2A process.