Dáil Éireann Debate, Tuesday - 24 July 2018

Tuesday, 24 July 2018

Ceisteanna (537)

Niamh Smyth

Ceist:

537. Deputy Niamh Smyth asked the Minister for Education and Skills the status of works for a school (details supplied); the timeframe for same; the contractor appointed; and if he will make a statement on the matter. [33641/18]

Amharc ar fhreagra

Freagraí scríofa

I am pleased to inform the Deputy that construction works commenced on the building project at the school referred to by the Deputy on June 28th, 2018. The Main Contractor is Tracey Brothers Ltd. and it is envisaged that the project will take approximately 27 months to complete.