Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 24 July 2018

Tuesday, 24 July 2018

Ceisteanna (591)

Charlie McConalogue

Ceist:

591. Deputy Charlie McConalogue asked the Minister for Education and Skills if a new building extension to a school (details supplied) will commence in autumn 2018; the status of the project; and if he will make a statement on the matter. [34725/18]

Amharc ar fhreagra

Freagraí scríofa

As the Deputy may be aware, the project to which he refers has been devolved for delivery to the local Education and Training Board (ETB).

The project is currently in the early stages of the architectural planning process. In this regard, the stage 1 submission is currently being examined in my Department. The outcome of this examination will be conveyed to the ETB as soon as it is available.

It is not possible to provide a timeline for the construction phase of the project until it has passed through architectural planning, including the statutory planning processes and the tender phase.

Barr
Roinn