National Broadband Plan

Dáil Éireann Debate, Tuesday - 23 July 2019

Tuesday, 23 July 2019

Ceisteanna (2252)

Michael Moynihan

Ceist:

2252. Deputy Michael Moynihan asked the Minister for Communications, Climate Action and Environment the status of the national broadband plan; and if he will make a statement on the matter. [33237/19]

Amharc ar fhreagra

Freagraí scríofa

The National Broadband Plan aims to ensure that every home, school and business in Ireland has access to high speed broadband. This is being achieved through a combination of commercial investment across the country, and a State intervention in those areas where commercial operators acting alone are unlikely to invest. The NBP has been a catalyst in encouraging investment by the telecoms sector. In 2012, less than 700,000, or 30% of Irish premises had access to high speed broadband. Today, 75% of the 2.4 million premises in Ireland can access high speed broadband. I recently brought a recommendation to the Government to confer preferred bidder status on Granahan McCourt, the remaining bidder in the NBP procurement process, and the Government agreed to this at its meeting on 7 May.

The Government Decision of 7 May 2019 means that it is intended to award the State Intervention contract to the Bidder subject to contract close and the finalisation of financial and legal requirements; this work is progressing. Deployment of the NBP State Intervention network will commence shortly after that.

The Bidder has indicated that the NBP State intervention will take an estimated 7 years from the beginning of deployment.

A deployment plan will be made available by the Bidder once the contract is signed. In the first year of roll out, the Bidder will deploy approximately 300 Broadband Connection Points (BCPs) across all counties. It is anticipated that between 7 and 23 BCPs will be deployed in each county. BCPs will provide a community based high speed broadband service, enhancing online participation and allowing for the establishment of digital work hubs in these locations.

The Bidder is aiming to pass 133,000 premises at the end of the second year, with 70-100,000 passed each year thereafter until roll out is completed.