Léim ar aghaidh chuig an bpríomhábhar
Gnáthamharc

Schools Building Projects

Dáil Éireann Debate, Tuesday - 5 April 2022

Tuesday, 5 April 2022

Ceisteanna (469)

Catherine Murphy

Ceist:

469. Deputy Catherine Murphy asked the Minister for Education the estimated amount her Department has spent to date on the major refurbishment works being carried out at a school (details supplied). [17704/22]

Amharc ar fhreagra

Freagraí scríofa

The major new school construction project for the school referred to by the Deputy commenced on site in November 2021. Works are progressing satisfactorily with a contract duration of approximately 26 months.

The contract amount is in excess of €12.4m and expenditure to date is in accordance with the conditions of the contract.

Barr
Roinn