I can confirm that the Office of Public Works has a number of scheduled refurbishment works to Garda Stations within the DMR to be carried out over the next six months. The Garda Stations and the nature of the works to be carried out are outlined in the table below and include works valued in excess of €100,000 which are funded either by the OPW or Garda Estate Management.
The Commencement dates for the scheduled works are subject to the final sign off of operational and design requirements by An Garda Síochána and where necessary, a successful tendering process.
Garda Station
|
Nature of the works
|
Works Due for Commencement
|
Bray Garda Station
|
Atrium Roof Replacement
|
Q2/3-2023
|
Cabinteely Garda Station
|
Painting, including repairs to plaster
|
Agreed to be carried out in phases over the next year
|
Cabinteely Garda Station
|
Showers on Ground Floor
|
On Site
|
Crumlin Garda Station
|
Repurpose Radio Workshops
|
Work to commence Q4-2022
|
Dun Laoghaire Garda Station
|
UA Works to Public Area and Ancillary Works
|
On Site
|
Ronanstown Garda Station
|
New Changing Facilities
|
On Site
|
Enniskerry Garda Station
|
Fabric Upgrade Works
|
On Site
|
Kevin Street Garda Station
|
Glazing Replacement
|
Q2-2023
|
Kilmainham Garda Station
|
Fabric Upgrade Works the “The Stables” building
|
Q2-2023
|
Pearse Street Garda Station
|
Roof Works
|
On Site
|
Cabra Garda Station
|
Refurb/Reconfigure Portacabins
|
Q2/Q3 2023 tbc
|
Coolock Garda Station
|
Conversion of Container to Storage
|
Q3-2023 tbc
|
Coolock Garda Station
|
Refurb Existing External Outhouses
|
Q3-2023 tbc
|
Finglas Garda Station
|
Repair of Tower Glass Façade
|
Q3 2023
|
13 A O’Connell Street
|
Refurbishment and Fitout Works
|
On Site
|
Malahide Garda Station
|
Attic Maintenance and Repairs to Roof
|
Q2 2023
|
Garristown Garda Station
|
Driveway Resurface and possible Accessibility Works
|
Q1/Q2 2023
|
Swords Garda Station
|
Canteen Refurbishment
|
Q1/Q2 2023
|