Schools Refurbishment

Dáil Éireann Debate, Tuesday - 14 February 2023

Tuesday, 14 February 2023

Ceisteanna (333)

Rose Conway-Walsh

Ceist:

333. Deputy Rose Conway-Walsh asked the Minister for Education when refurbishment works at a school (details supplied) will be completed; and if she will make a statement on the matter. [6700/23]

Amharc ar fhreagra

Freagraí scríofa

The building project for the school referred to by the Deputy achieved sectional Substantial Completion on in September 2022. The project brief was for the construction of a new 650 pupil Post Primary School on a green field site to incorporate a multi-use hall, ancillary rooms and all associated site works. Full Substantial Completion is expected in March 2023.